PIMA Freeway

Overview:

This major freeway expansion project delivered a new 6.1-mile section of freeway through a highly developed area of Scottsdale, Arizona, improving regional mobility and providing grade-separated access across one of the Phoenix metropolitan area’s fastest-growing corridors. Completed through a partnership between Ames Construction and Edward Kraemer & Sons for the Arizona Department of Transportation (ADOT), the project required extensive roadway, bridge, utility, and retaining wall construction within a constrained urban environment.

Project Overview:

This $81.8 million lump-sum project involved construction of 6.1 miles of new freeway through Scottsdale, Arizona. The corridor was designed with a depressed four-lane divided highway along the southern portion of the project and an elevated roadway section through the northern portion. Kraemer served as a key construction partner to Ames Construction, performing significant bridge and infrastructure work while overcoming restricted right-of-way conditions and extensive utility conflicts throughout the corridor.

Key Infrastructure Improvements:

  • Construction of 6.1 miles of new freeway through a densely developed urban corridor
  • Construction of 12 new bridges providing grade separation at all major cross streets
  • Development of depressed freeway sections in the southern half of the project and elevated freeway sections in the northern half
  • Installation of more than 200,000 linear feet of sewer, water, and storm drainage infrastructure
  • Completion of approximately 2.3 million cubic yards of earthwork
  • Construction of approximately 27,000 square feet of retaining walls to accommodate limited right-of-way conditions
  • Installation of more than 150,000 square feet of noise barrier walls to minimize impacts on surrounding neighborhoods
  • Placement of approximately 385,000 square feet of concrete paving throughout the corridor

Project Timeline and Performance:

The project was constructed between July 1998 and June 2001. Careful coordination was required to maintain progress within a highly urbanized environment while managing extensive utility relocations and complex bridge construction activities. The project team successfully delivered the corridor improvements while accommodating significant infrastructure challenges associated with constructing a major freeway through an established community.

Community Impact:

The new freeway corridor improved regional transportation capacity and reduced congestion while enhancing safety through the elimination of at-grade crossings. Extensive noise barrier walls and strategically designed retaining walls helped minimize impacts on adjacent neighborhoods and businesses. The project’s utility improvements also modernized critical underground infrastructure, benefiting the surrounding community long after construction was completed.

Project Significance:

This project demonstrated Kraemer’s ability to successfully deliver complex urban transportation infrastructure in partnership with leading contractors on behalf of ADOT. The combination of large-scale earthwork, bridge construction, utility relocation, retaining structures, and roadway construction showcased the team’s expertise in executing multifaceted freeway projects within heavily developed metropolitan environments.