US 6 Design-Build
Overview
The CDOT US 6 Bridges Design-Build project transformed one of the most heavily traveled and complex transportation corridors in the Denver metropolitan area. Located at the critical interchange of I-25 and US 6, the project reconstructed aging infrastructure, improved traffic operations, enhanced multimodal connectivity, and increased long-term system reliability. As the prime design-build contractor, Kraemer delivered innovative solutions that reduced costs, accelerated construction, and minimized impacts to the traveling public.
Project Overview:
This $108.2 million design-build project (original contract value of $97 million) reconstructed the major interchange and bottleneck at I-25 and US 6 in central Denver. Serving daily traffic volumes of approximately 214,000 vehicles on I-25 and 144,000 vehicles on US 6, the project required extensive bridge replacement, roadway reconstruction, utility coordination, and traffic management in one of Colorado’s busiest urban transportation corridors. Kraemer served as the prime design-build contractor with Felsburg, Holt & Ullevig (FHU) as the design partner. The team’s innovative approach to phasing, alignments, and pavement design generated approximately $8 million in savings for CDOT compared to the next-best proposal.
Key Infrastructure Improvements:
- Replacement of six existing bridges and construction of six new bridges for a total of 12 bridge structures
- Construction of structures spanning major transportation corridors, including I-25, US 6, Union Pacific Railroad, BNSF Railway, RTD light rail, and the South Platte River
- Realignment of Ramp B from northbound I-25 to westbound US 6 to improve traffic flow and weaving conditions
- Construction of new collector/distributor roads and ramp structures to improve interchange operations
- Implementation of revised paving materials designed to provide a 30-year pavement life and reduce long-term maintenance costs
- Construction of a new bicycle and pedestrian bridge connecting Barnum Park North and South
- Upgrades to three City and County of Denver parks within the project area
- Replacement of a critical Denver Water transmission line and relocation of major utilities while maintaining public access and transit operations
- Reconstruction of Knox Bridge as an added project enhancement
Project Timeline and Performance:
The project was originally scheduled from July 2013 through September 2016; however, Kraemer completed construction in November 2015, finishing approximately 10 months ahead of schedule. A key component of this success was the team’s “slow down to speed up” strategy, which delayed the start of construction by seven months to allow for extensive planning, stakeholder coordination, and risk mitigation. Innovative construction staging included an early full roadway closure over a three-day weekend that eliminated an estimated 30 days of traffic impacts. Major activities such as girder erection, bridge demolition, deck pours, paving, retaining wall construction, and drainage work were completed during nighttime hours to minimize disruptions and accelerate delivery. Throughout construction, crews worked adjacent to live traffic volumes reaching as many as 10,000 vehicles per hour during peak periods.
Community Impact:
The project significantly improved mobility, safety, and connectivity within central Denver while minimizing impacts to the traveling public. New pedestrian and bicycle connections restored safe access between Barnum Park North and South, which had long been separated by the highway corridor. Extensive coordination with transit providers, utility companies, local agencies, and community stakeholders ensured continued access throughout construction while modernizing critical transportation and utility infrastructure for future generations.
Project Recognition:
The CDOT US 6 Bridges Design-Build project received the DBIA Transportation Project of the Year Award and four additional regional and national industry honors. The project has been recognized as a model design-build transportation project due to its innovative delivery approach, accelerated schedule, cost savings, and successful management of complex urban construction challenges. CDOT leadership specifically cited Kraemer’s competitive pricing, innovative phasing concepts, and aggressive schedule management as key factors in the project’s success, while project partners have continued to reference the project as a benchmark for effective design-build delivery in Colorado.